Craig Wells at Quelfire shares insight from a panel debate that discussed progress of the UK’s Building Safety Act’s Gateway regimes
Image credit: shutterstock/Joseph Oropel
Gateway 2 has changed the way higher-risk building projects approach design, accountability and evidence. As the industry moves towards Gateway 3, however, another question is coming into focus: what happens when a building that has been approved on paper needs to demonstrate that it has been built in accordance with that approval?
That was one of the key issues we discussed when I sat down with Graeme Whitty of Willmott Dixon and Nasar Ishfaq of R5 Consultants for a panel discussion at London Build 2025.
Having worked through Gateway 2, I think there are some clear lessons emerging for the industry. Accountability, collaboration and, importantly, the need to think about evidence much earlier in a project all came through strongly in our discussion.
Accountability
One of the most significant changes brought about by the Building Safety Act is the greater emphasis on accountability throughout a project.
Ishfaq described the Principal Designer’s (PD) role as being primarily about coordination and
identifying gaps between stakeholders. His team takes responsibility for bringing those parties together and providing leadership.
Whitty explained how Willmott Dixon approaches this, with project teams kept at the centre of decision-making. He also stressed the importance of the Main Contractor understanding the responsibilities of individual subcontractors before information is passed to the PD.
That can be difficult when different organisations and teams are brought together for the first time.
“You might be given a design team that you’ve not worked with before, different expectations, different standards. You have to unpick that,” Whitty said.
The issue of responsibility also comes into sharp focus at the end of a project. As Principal
Contractor, the team signs a declaration confirming that the project has been built in accordance with applicable regulations.
That makes it all the more important that everyone understands their responsibilities from the beginning, rather than trying to establish who is responsible when a Gateway deadline is approaching.
Collaboration
Firestopping brings together a number of different disciplines. The architect determines where the walls are located, the structural engineer specifies the size and location of openings, and the M&E engineer identifies what will pass through those openings and where services will be located. Only then can the appropriate firestopping system be selected against the relevant test evidence.
A decision made by one discipline can have consequences for another, potentially leaving a solution that does not align with available test evidence. That can mean redesign, delays and additional cost further down the line.
This is why I believe firestopping needs to be part of the conversation much earlier. It shouldn’t be a case of reaching the later stages of a project and then trying to find a product that works with what has already been designed.
The next test
The industry has understandably spent a lot of time getting to grips with Gateway 2. Gateway 3 is now the next big unknown.
Ishfaq raised concerns about the potential for delays, particularly in light of some of the difficulties experienced with Gateway 2. He also felt that Gateway 3 has not yet been “road tested enough” for its full impact to be understood.
We may not yet know exactly how the process will work in practice, but that is not a reason to wait before preparing for it. One of the clearest lessons from Gateway 2 is that Gateway 3 cannot be treated as something to deal with at the end of a project.
Whitty described Gateway 3 as being about successful execution and demonstrating that what has actually been built matches what was submitted and approved at Gateway 2.
That has implications for the way evidence is gathered throughout construction. You cannot wait until the end of a project to demonstrate how, for example, piling was installed. The process for recording that information needs to be considered before the work begins.
Early preparation
Whitty explained that project teams now get together before work begins to discuss what is going to be built, what evidence they will need to produce, how often it needs to be collected and, more generally, what “good” looks like.
There is a practical benefit to this as well as a compliance one. According to Whitty, having these conversations early has helped production and efficiency and generally led to fewer conflicts on site.
That is an important point. The Gateway process can easily be seen as another layer of approval and paperwork, but if the requirements are built into the project from the beginning, they can actually encourage better planning.
Demonstrating compliance
Ishfaq highlighted the importance of considering the procurement of the design, product and system when preparing a Gateway submission. Reviewing information early and agreeing clear deliverables allows contractors to take a more systematic approach to presenting evidence to the Building Safety Regulator (BSR).
Whitty also emphasised the need for transparency around the products and systems being used.
His advice was straightforward: make the process as easy as possible for the regulator to follow. Explain the decisions that have been made, provide examples where appropriate and be clear about why particular products or systems have been selected.
Again, the earlier these decisions are made, the easier it should be to demonstrate compliance later.
What comes next?
There is still uncertainty around how Gateway 3 will work in practice. But one thing that came through clearly from our discussion is that the industry should not wait for every detail to be settled before preparing for it.
Gateway 2 has shown the value of bringing people together earlier, being clear about responsibilities, agreeing products and systems and thinking about the evidence required before construction begins.
For firestopping, in particular, that means moving away from the idea that fire safety can be dealt with later in the programme. The design, the construction process and the evidence needed to demonstrate compliance all need to be considered together.
Whether it is a 32-storey residential building or a single-storey school, the principle is the same – design for safety, build in accordance with that design, and make sure there is clear evidence to demonstrate that it has been achieved.

Craig Wells is Sales Director at Quelfire. He brings over a decade of experience in passive fire protection. His understanding of commercial pressures, regulatory demands, and on-site realities allows him to support both internal teams and empower external stakeholders with clarity and confidence. Craig speaks with passion and a genuine intent to drive cultural change to enable safer buildings for all.