The Building Safety Regulator has reported rising Gateway 2 approvals alongside improved outcomes for existing building remediation
Image credit: Shutterstock/I Wei Huang
The Building Safety Regulator (BSR) has reported an increase in Gateway 2 approvals, with 84% of applications approved during the latest 12-week rolling period to 31 August 2026.
The approval rate increased from 82% in the previous reporting period, with 287 of 340 building control decisions approved across higher-risk building (HRB) categories. The approvals represent 18,029 residential units.
Approval rates for new higher-risk buildings (HRBs) and conversions reached 92%, excluding invalidations and withdrawals, with 9,362 residential units receiving approval.
The median determination time for these applications was 22 weeks.
Gateway 2 approvals improve for new-build and conversion projects
London accounted for 31 of the 50 national decisions on new-build projects during the period, with 28 applications approved.
This represents a 90% approval rate in the capital and covers 4,477 residential units. The median determination time for non-complex applications in London was 23 weeks.
BSR said the latest figures represent a significant improvement compared with the 12 weeks to August 2025, when the median approval time was 43 weeks and the approval rate stood at 39%.
Nationally, BSR is currently managing 147 live new-build and conversion applications covering 32,691 individual units.
There are also 33 complex cases under active management, with a national median determination time of 33 weeks. London accounts for 23 of these cases.
The regulator has also closed the single remaining long-term legacy case, which had been managed as a complex application because of significant technical challenges.
Gateway 2 approvals improve for new-build and conversion projects
Existing building remediation approvals also increased during the latest reporting period, reaching 89% nationally compared with 85% previously.
BSR determined 118 remediation applications, approving 105 projects covering 8,667 residential units. In London, the remediation approval rate reached 96%, covering 3,936 units.
The regulator said measures introduced through its external remediation plan in April 2026 have helped improve the processing of applications.
The number of remediation applications dating from 2024 has also fallen from 42 at the start of the year to 12.
BSR currently has 327 active remediation cases nationally, representing 28,274 residential units.
The number of new-build projects that have commenced work has risen to 126.
New-build inspections identify cases requiring remedial work
BSR said its expanding inspection programme has identified a small number of cases where construction work has not conformed to agreed designs and has required remedial work.
The regulator said it will continue to monitor these cases and take action where appropriate to ensure approved designs are translated into safe buildings.
NHS applications record 82% approval rate
BSR made 22 determinations on NHS building control applications during the latest 12-week period, approving 18 for an 82% national approval rate.
The median determination time was 22 weeks, although applications submitted during 2026 have a median determination time of 13 weeks, with some recent projects receiving approval within the statutory eight-week timeframe.
London recorded a 78% approval rate, with seven projects approved from nine determinations.
BSR is currently managing 32 active NHS building control cases nationally.
Refurbishments account for 43% of Gateway 2 decisions
Category A and B internal refurbishments accounted for 143 decisions during the latest 12-week period, representing 43% of all Gateway 2 decisions.
The approval rate for these applications was 78%, with a median determination time of 32 weeks.
For refurbishment applications submitted during 2026, the median determination time has fallen by 50% to 16 weeks. BSR is currently overseeing 1,082 active internal refurbishment cases.
The regulator has also reported early activity at Gateway 3, with 346 applications received to date. Of these, 260 relate to internal refurbishments, while 45 are transitional cases and 23 concern NHS internal refurbishments.
During the latest 12-week period, BSR determined 16 Gateway 3 applications, achieving an 88% approval rate with a median determination time of 20 weeks. The quickest approval was completed in seven weeks.
There are currently 105 active Gateway 3 cases for internal works, 15 for NHS works and eight for external remediation. No new-build developments that have passed through Gateway 2 have yet progressed to an active Gateway 3 assessment.
BSR expands technical workforce
BSR said it has expanded its technical resources to support the volume of building safety decisions.
Its current regulatory workforce comprises 177 internal BSR core staff working alongside 508 external technical specialists.
Of the external specialists, 64 are integrated into the Innovation Unit or external remediation teams, including 36 registered building inspectors, eight fire service professionals and 20 structural engineers.
The regulator said it is continuing to scale its technical capacity in anticipation of future demand.
Telecoms work rules change
New arrangements for certain telecommunications work in higher-risk buildings also came into force on 1 September 2026.
Eligible work involving fibre-optic cabling and rooftop mobile mast installations can now proceed without prior notification to or approval from BSR before work begins.
For fibre-optic cabling, duty holders will need to notify BSR after completion, while eligible rooftop telecoms mast installations will require a completion certificate application.
BSR said the changes are intended to introduce a more proportionate approach while maintaining core building safety and compliance requirements.
‘Continued progress’
Charlie Pugsley, Acting Chief Executive Officer of the Building Safety Regulator, said the latest figures demonstrate continued progress in building control assessments and approvals.
“Our latest performance figures show that we are successfully driving momentum in building control assessments and approvals for more than 18,000 residential units.
“Overall gateway 2 approvals have reached 84% with new HRBs currently tracking at 92%, while remediation projects are moving through the system much faster, achieving an 89% national approval rate. This progress is a direct result of our expanded technical workforce and closer, earlier collaboration with applicants.
“While we are pleased to see determination times reducing, particularly for new builds under our Innovation Unit, existing remediation projects and key NHS developments, we remain steadfast in our core mission.
“As buildings progress through the inbuild phase to Gateway 3, we continue to enhance and refine systems and processes to ensure that safe designs are translated into safe buildings.
“As we continue to streamline our processes and introduce proportionate building control updates, such as the recent telecommunications measures, the safety of residents and our communities remains at the heart of what we do.
“The strict duty holder, functional and competence requirements of the Building Safety Act and Building Regulations remain fully in force to protect the public.”